20 CXRC-SVX01F-EN
Pre-Start Checklist
After the unit is installed, complete each step in the
checklist that follows and check off each step as completed.
When all are accomplished, the unit is ready to be started.
• Inspect all wiring connections. Connections should be
clean and tight.
• Check voltage to the unit at the line power fused
disconnect. Voltage must be within the voltage
utilization range given on the unit nameplate. Voltage
imbalance must not exceed two percent. Refer to the
“Voltage Imbalance,” p. 17.
• Check condenser fans. Condenser fan blades should
rotate freely in the fan orifices and should be mounted
securely on the motor shafts.
• Check condenser coils. Coil fins should be clean and
straight.There should be no restrictions to proper
airflow through the condenser.
• Evacuate the refrigerant system. See Maintenance
chapter of unit IOM (SCXF-SVX01*-EN or SCXG-
SVX01*-EN for evacuation and procedure.
• Once the system is properly evacuated, charge each
circuit with proper amount of refrigerant. See
Installation-Mechanical and Start-up chapters of unit
IOM (SCXF-SVX01*-EN or SCXG-SVX01*-EN for
refrigerant charging procedures.
• Prepare remainder of system for operation and
coordinate condenser start up with evaporator unit
startup.